Question.1452 - Using a lot-for-lot ordering strategy for the following item, what is the planned order release amount in week 3? (Note: Use a lead time of one week and the gross requirements and scheduled receipts depicted below, and assume you begin with 50 units in inventory.) Week 1 2 3 4 Gross requirements 0 100 80 15 Scheduled receipts 25 0 0 0 Projected ending inventory (50) Net requirements Planned order receipts Planned order releases
Answer Below:
unitsMore Articles From Operation Management