Question.1453 - The master production schedule (MPS) for two products, A and B, is shown below. To manufacture item A, two units of component C are required. To manufacture item B, four units of component C are required. The inventory balance for C is 10 units at the start of week 1. Using this information, determine the gross requirements for component C to start week 1. MPS Week 1 Product A 15 Product B 2
Answer Below:
unitsMore Articles From Operation Management